2021 Annual Paving Project

Project Update

The design phase is complete and the project is advertised for contractor bids. The Engineer's opinion of probable construction cost is $1,400,000. The bid open is scheduled for May 11.

Project Details

  • No. of street segments: 14
  • Quantity of paving: 5,300 tons
  • No. of curb ramp improvements: 24
  • Design team: The Blueline Group
  • Contractor: TBD
  • Construction contract amount: TBD
  • Construction Management team: The Blueline Group
  • Public notification postcard

Project Timeline

BenchmarkDate
End constructionSeptember
Begin constructionJune - July
Pre-construction meetingJune
Award construction contractMay 25th
Bid OpenMay 11th
Advertise for contractor bidsApril 26th
Design phaseFebruary - April
Award Design contractJanuary 26th
Design and CM Services InterviewsJanuary 13th
SOQ dueJanuary 6, 2021
Issue RFQ for Design and CM ServicesDecember 16th
Project authorized by CouncilJanuary 21, 2020


Map of streets to be repaved in 2021

2021, overlay, paving

2021 Street List

Street
Begin End
152nd St SE 173rd Ave SE 174th Ave SE
157th Pl SE 179th Ave SE east end
161st St SE east of Tatty Ave SE east end
173rd Ave SE 149th St SE 152nd St SE
174th Ave SE 152nd St SE 154th St SE
176th Ave SE 161st St SE W Main St
182nd Ave SE north end 154th St SE
Academy Way W Main St south end
Ann St US 2 E Main St
Foye Ln north end W McDougall St
Monroe St Park St Kelsey St
Morris St W Main St Pike St
Orr St north end W Hill St
Park Ln 159th St SE west of Dickinson St
Pike St Kelsey St S Madison St
Roberts St Park St S Sams St
W Maple St west end Kelsey St
W McDougall St Sams St S Blakeley St

157th Place SE

Existing pavement1