Madison Sewer Separation
Project Description
This project will remove the storm water runoff from entering the sanitary sewer system by collecting, treating and infiltrating the runoff. It is proposed to use Filterra Systems to treat the runoff prior to infiltration and install permeable sidewalks to reduce the runoff to the infiltration basin. In conjunction with this work, the City will replace an old 4" water main and reconstruct the street to eliminate the excessive crown from past overlay projects.
Contact Us
Jammi Guion
Contracts Supervisor
Email Public Works Contracts
Phone: 360-863-4514Jim Gardner, PE
Project Manager
Email Jim Gardner
Phone: 425-754-1868Scott Peterson, PE
Deputy City Engineer
Email Scott Peterson
Phone: 360-863-4606
The City is reaching out to the residents along North Madison for their input on the preferred layout for the Madison Combined Sewer Separation Project. Staff has prepared a response method using SurveyMonkey to allow citizens to provide input. Drawings and survey access links are located below:
The City will also send out postcards to owners and place informational hangers on resident doors by March 4th. The survey will end and the above link will be removed on March 28th. You input is important to us and the effort to respond is greatly appreciated.
Project updates
April 28, 2022
City staff working on PS&E package. Anticipate submittal to Ecology by May 5th.
March 30, 2022
City had consultant complete a 'Constructability Review' and is working on changes to plans, specifications and estimate (PS&E). Anticipate submitting PS&E package to Ecology by April 27th.
Feb 28, 2022
Staff made changes per ECY comments and resubmitted the PS&E set to ECY for approval 2/24/2022. Anticipate 45 day review period.
Jan. 31, 2022
City staff expects to receive Ecology response on 90% drawings by mid February.
Jan. 4, 2022
Staff has completed the 90% drawings and they are currently being reviewed internally.
Nov. 30, 2021
City Staff is working on design. Construction to begin in Summer 2022
Oct. 28, 2021
City Staff is working on design. Construction to begin in Summer 2022
Sept. 29, 2021
City Staff is working on design. Construction to begin in Spring 2022
Sept. 1, 2021
City Staff is working on design. Construction to begin in Spring 2022
July 29, 2021
City Staff working on design. Construction to begin in Spring 2022
June 28, 2021
City Staff working on design. Construction to begin in Spring 2022
May 26, 2021
City Staff has, after several meetings and discussions, review of citizen comments, review of survey results and verifying compliance with City Code come to the following design criteria. The road will have 10-foot drive lanes and 8-foot parking lanes per City standards, the back of new sidewalks will remain at the same location as the back of the existing sidewalks, the City will pay the extra cost to install regular concrete for the sidewalks, the sidewalk along the east side of Madison from Main Street to the north side of the church property will extend to the new curb, bulb-outs will be redesigned so that no legal parking spaces are lost along the street, existing paths through the planter are will be replaced with concrete matching the existing width.
April 26, 2021
City is still discussing Citizen comments and concerns before proceeding with the design.
March 29, 2021
City held a public meeting with residents to discuss the project. The on-line survey period has ended. Staff is reviewing comments from the meeting and survey. Waiting for Ecology approval of Design Report. Will begin work on 90% drawings after completion of survey review.
March 1, 2021
Staff posted survey monkey to this site for Citizen response.
February 28, 2021
Staff is working on virtual open house for public comment. Notices will be mailed to property owners and door hangers placed on residences and businesses to notify renters. Look for these to come out in mid March.
January 28, 2021
Staff reviewing design drawings. Design Report submitted to Ecology for review.
December 30,2020
Staff is preparing for a virtual public review and comment, preparing suitable drawings and preparation of notifications of residents and property owners.
November 30,2020
Design 60% drawings being worked on by staff. Current schedule has project being advertised in May 2021.
October 29,2020
30% design drawings under review. Current schedule has project being advertised in May 2021.
September 29,2020
Senior Engineer working on 30% design drawings.
August 27,2020
Project currently being designed.
Benchmark | Date |
---|---|
Apply for Grant | 11/8/2016 |
Grant offered to City | 4/23/2018 |
Comprehensive Plan Approved | 6/13/2019 |
Council acceptance of Grant | 8/27/2019 |
Project Authorization by Council | 1/27/2020 |
Begin Project Design | 1/28/2020 |
Covid Delays Begin | 3/23/2020 |
Geotech Work Resumes | 6/5/2020 |
Design completed | 5/2/2022 |
Advertise for Construction | 5/18/2022 |
Begin Construction | 8/1/2022 |
Construction Complete | 11/11/2022 |