DOC Reservoir No. 2

Project Description

This water utility project will construct a second water reservoir on the Department of Corrections (DOC) property. This facility will increase the fire flow capacity of the corresponding water pressure zone.

For more information, please contact the project manager:
Kim Klinkers, PE
(360) 863-4531
Email

Project Updates

City engineering staff are in initial conversations with the Department of Corrections. Later this year, the City will advertise a Request for Proposals to select an engineering firms to design this project. The design phase will be ongoing throughout 2019 and likely into a part of 2020. The City intends to begin construction in 2020. 

Project Timeline

Key Benchmark Date
Authorize Project by City Council January 22, 2019
Advertise for Design RFP April, 2019
Begin Design Phase June, 2019
End Design Phase April, 2020
Advertise for Contractor Bids May, 2020
Begin Construction July, 2020
Construction Complete February, 2021