132nd Street SE Water Main Replacement

Project Description

This capital project will replace approximately 3,200 feet of aging water main under 132nd Street SE, which is located in unincorporated Snohomish County. New fire hydrants and residential service connections to existing are also part of this project. The design phase was accomplished in 2018, followed by construction in 2019.

City engineering staff completed the design in 2018. The project was advertised to the public for contractor bids in January, 2019. SRV Construction Inc was the lowest bidder and will be awarded the contract to perform the work. Construction is anticipated to begin the last week of March.

For more information, please contact the project manager:
Jim Gardner, PE
(360) 863-4542
Email

Updates

The project construction is substantially complete. Some minor cleanup work may still exist, but construction activity is essentially complete.

Project Benchmarks Targeted Date
Project Authorization January 16, 2018
Design Phase Begins January 17, 2018
Design Phase Completed December 31, 2018
Bid Advertisement January 9, 2019
Construction Begins March 11, 2019
Construction Ends May 17, 2019
132nd Vicinity Map